From Finland to Vietnam: The Epic Journey of Two Mantsinen 300ES Cranes

From Finland to Vietnam: The Epic Journey of Two Mantsinen 300ES Cranes

In a logistical feat spanning continents, two 400 MT Mantsinen 300ES cranes, known for their heavy-duty efficiency, embarked on a 27,800-kilometer journey by sea from the Port of Rauma, Finland, to Dung Quat, Vietnam. The project was a collaborative effort involving UTC's Global Heavy Equipment Group, UTC Overseas Finland, and their partners who expertly navigated the challenges of transporting these rail-mounted behemoths.

Mantsinen 300ES Cranes

The Mantsinen 300ES cranes are among the world’s most efficient material handlers, capable of tackling the toughest operations. While their size and width are crucial for their functionality, they present unique challenges during transport, especially for a journey of this magnitude.

To address the challenges posed by the size of the cranes, Vuorsola provided new self-propelled modular transporters (SPMTs). These cutting-edge transporters ensured the safe and smooth handling of the machines at every stage of the process. The team also worked closely with the port authorities and stevedores to create space in the container yard, enabling seamless operations during the loading phase.

Despite the complexity of the task, meticulous planning and collaboration paid off. After positioning the cranes, the weather cleared, and the sun broke through—a fitting sign for the smooth lifts and absence of delays that followed.

Mantsinen two 300ES Shipping, Vietnam, Dung Quat-17
Mantsinen two 300ES Shipping, Vietnam, Dung Quat-7

Teamwork

The transport required seamless coordination between all parties involved. The collaboration with port authorities and stevedores not only ensured operational efficiency but also highlighted the importance of teamwork in large-scale international projects.

The cranes were unloaded at Dung Quat, Vietnam, where they underwent rigorous testing to ensure they were fully operational. The project was an exciting challenge, leaving the team with a sense of pride in their achievement.

As the cranes are prepared to begin their heavy-duty operations in Vietnam, the successful journey stands as a testament to UTC’s power of innovation, collaboration, and meticulous planning in overcoming logistical challenges on a global scale.

featured image showing UTC Managing transport for a Chilean Solar Plant

Chile Solar Plant Transport

August 25, 2021

UTC Chile recently moved a three-phase power transformer across South America for a long-time client. Manufactured in Brazil, the unit was transported to the Atacama Desert in Chile for installation in a substation that is part of a large solar plant project in the region.

Featured image showing the UTC Overseas logistics crew use a heavy-lift vessel at Port of Houston to load cranes for transport.

Tight Deadlines & Fast Planning

July 28, 2021

UTC’s Heavy Equipment experts move cranes and equipment of all sizes and weights around the globe.